Electromechanical Equipment Installation at the Shwegyin Hydropower Station, Myanmar
Date:2016-06-17 VisitCount: Font size:[ L M S ]

 Electromechanical Equipment Installation at the Shwegyin Hydropower Station, Myanmar

Electromechanical Equipment Installation at the Shwegyin Hydropower Station, Myanmar

 

Installed capacity:80MW(4×20MW)

Construction period:2010—2011

Contract type:EPC

Financier:the owner

Description: CGGC designed, provided and installed four 20MW Francis turbine generator units for the Shwegyin Hydropower Station in Myanmar.