Gravel System of LB Hydropower Station of CC/LB Hydropower Project in Argentina Put into Trial Operation
Date:2019-10-11 VisitCount: Font size:[ L M S ]


Scene of the Ceremony


Gravel System

On October 8, the LB Hydropower Station of CC/LB Hydropower Project in Argentina held the trial operation ceremony for its gravel system, marking the completion and commissioning of the overall gravel system of LB Hydropower Station. Among the attendees were Li Tieying, Head of the Working Group of CGGC, He Xiongfei, Assistant General Manager of CGGC and General Manager of CC/LB Hydropower Project in Santa Cruz of Argentina, Gabriel Morinigo, Site Manager of the owner, supervision engineer Antonio Sabatini, etc.

At the ceremony, He Xiongfei noted that the operation of gravel system marks that LB Hydropower Project has entered in a new phase. He hoped all the personnel could keep forging ahead to complete all the construction tasks and benefit local people as soon as possible.

The gravel system started immediately upon receiving the commencement instruction issued by supervision engineer Antonio Sabatini, and worked in good order from forwarding, screening and washing of raw gravel materials to separation of finished aggregate.

The construction site suffered extreme weathers like strong wind since the spring, which makes system installation even more difficult. Facing this, all personnel of the consortium took all kinds of measures despite of cold weather and frequent strong wind, successfully completing the single unit commissioning and debugging, and finally putting the system into trial operation.

After being put into operation, the gravel system is capable of processing 600 tons of aggregate hourly, which can fully meet the demands for concrete production and dam pouring.